Construction, Civil, Structural, Mechanical, Electrical & Instrumentation and Fabrication

Cruzan CMS Recovery Project Expansion

EXCEL worked as the general contractor for all civil, structural, mechanical, electrical, and instrumentation work for the Cruzan Rum Facility.

Location

St. Croix, U.S. Virgin Islands

Contract Value

$25 Million

Duration

12 Months

Markets

Food & Beverage

Project Status

Complete
Cruzan CMS Project
Eagle Award

Project Description

This EPC (engineering, procurement, construction) project comprised the complete construction of a new wastewater treatment facility from design engineering to start-up. Over 6.5 million pounds of pipe, structural steel, concrete piles, facility, and construction equipment, storage tanks, cable, and wire were shipped or barged to the island from the U.S. mainland and other countries to construct this project. Although a tropical storm and two hurricanes created numerous challenges, the schedule was met and completed with no OSHA-recordable incidents.

Quantity Installation Summary

285 Precast Concrete Piles
2,500 CY Concrete
120 Tons Structural Steel
12,000 FT Stainless Steel Pipe
2,000 Ft CPVC Pipe
60 EA Mechanical Equipment
94 EA Electrical Equipment
1,344 Stainless Steel Welds
605  Valve Installations
103 Hydrotest Packages
8,000 SQFT RO Building
1,000 FT Cable Tray
12,000 FT Conduit
200 FT Concrete Trench
12,000 FT Power Cable
15,000 FT Lighting Cable
1,500 FT Ground Grid System
500 FT Lighting Protection System
25,000 FT Instrument Cable
1,200 FT Devicenet Communcation Cable
500 EA Electrical Terminations
80 EA Electrica Function Tests
214 EA Instrument Installations
1,500 FT Instrument Process Tubing
2,500 FT Instrument Terminations
300 EA Instrument Loopchecks

Awards

  • ABC National Excellence in Construction Eagle Award

Other Construction Projects

Eagle Award
Complete

Semiconductor

Linde TSMC Semiconductor

Construction, Civil, Mechanical, Electrical & Instrumentation, Fabrication

View Project

Eagle Award
Complete

Oil and Gas, Renewable Energy

Valero Diamond Green Diesel 3

Construction, Mechanical, Electrical & Instrumentation

View Project

OCI Nitrogen Project Beaumont, TX
In Progress

Renewable Energy

OCI Nitrogen

OCI announces partnership with Louisiana and Texas-based EXCEL Group to construct all elements of a new Beaumont facility.

Construction

View Project

Exxon XTO Industrial Construction Project
Eagle Award
Complete

Oil and Gas

Exxon/XTO Cowboy Project

EXCEL completed the construction of a grassroots cryogenic gas plant in New Mexico.

Construction, Civil, Structural, Mechanical, Electrical & Instrumentation, Fabrication

View Project

Complete

Oil and Gas

EXXON #12 Deprop Turnaround

Excel Performed Fabrication and Mechanical Work.

Construction, Mechanical, Turnarounds, Fabrication

View Project

Complete

Chemical / Petrochemical

BASF PGM Refinery

Self-Performing Civil, Mechanical, Structural, and E&I

Construction, Civil, Structural, Mechanical, Electrical & Instrumentation

View Project

Altas V Vandenburg CA
Complete

Space & Aviation

Atlas V Project

Lockheed Martin, Complex 3-E Vandenburg Air Force Station and Complex 41 Cape Canaveral Air Force Station renovation projects

Construction, Electrical & Instrumentation

View Project

LIGO Livingston
Complete

Technology

LIGO Project

LIGO consists of two ground-based Michelson interferometers with Fabry-Perot arm cavities, operated in unison to detect gravitational waves directly.

Construction

View Project

KTI Saudi Aramco
Pyramid Award
Complete

Oil and Gas

KTI-Saudi Aramco Heater Revamp

EXCEL's scope on the KTI-Saudi Aramco Heater Revamp was demolition, performed pipe fabrication, and installed pipe and structural steel on the platformer consisting of four heaters.

Construction, Fabrication

View Project

Tu Hogar Renace STEP Program
Complete

Disaster Relief

Puerto Rico Fema Sheltering & Temporary Essential Power Program

EXCEL effectively balanced its goals of safety, quality, and homeowner satisfaction alongside requirements to meet production to deliver assigned repairs successfully.

Construction, Disaster Recovery

View Project

TDC Bitumen Unloading Project
Eagle Award
Complete

Terminals

TDC Bitumen Unloading Project

As an EPC contractor for TDC/Genesis Energy, EXCEL provided a total design and construction solution for their Bitumen Unloading facility.

Construction

View Project

Kinder Morgan tank terminal
Eagle Award
Complete

Terminals, Midstream

Kinder Morgan Geismar Logistics Center

As general contractor for the Kinder Morgan Geismar Logistics Center, EXCEL provided a total construction solution for Kinder Morgan's terminal project.

Construction

View Project

Nalco setting R1050 in place
Complete

Chemical / Petrochemical

Nalco R-1050 Reactor Replacement Expansion

EXCEL worked as the general contractor for this EPC contract to replace the 25-year-old R-1050 reactor with a larger, more efficient one.

Construction

View Project

Westlake Control Room Upgrade
Pyramid Award
Complete

Chemical / Petrochemical

Westlake Control Room Upgrade

EXCEL was selected as the general contractor for the Westlake Control Room Upgrade Project.

Construction

View Project

Get Started

Consult with an expert. Get a customized plan and budgetary estimate.

Want to stay up to date? Sign up to receive project updates and company news in your inbox.

We care about the protection of your data. Read our Privacy Policy.