Construction and Disaster Recovery
Puerto Rico Fema Sheltering & Temporary Essential Power Program
EXCEL effectively balanced its goals of safety, quality, and homeowner satisfaction alongside requirements to meet production to deliver assigned repairs successfully.
Location
Project Scope
Markets
Project Status
Project Description
From 2018 to 2019, as part of the most extensive FEMA Sheltering and Temporary Essential Power (STEP) program, EXCEL provided emergency repairs for approximately 12,000 structures across Southwest Puerto Rico following damages sustained during the 2017 Hurricanes Irma and Maria. These repairs were later supplemented with thousands of permanent roof repairs, funded through the same FEMA program. Additionally, with over 1,000 project personnel at its peak, EXCEL utilized local subcontractors and ensured the quality performance of our assigned scopes.
EXCEL encountered many challenges in this program due to its scale and logistics challenges as it is isolated from the continental United States. Our team's challenges included material availability, terrain logistics, instability, power, and communications infrastructure outages, and political pressures. In overcoming these challenges, the EXCEL Team learned many lessons about maintaining a rigorous production schedule while maintaining strict quality standards. EXCEL has incorporated these lessons into future programs, continually improving our performance and delivery.
In May 2019, EXCEL's performance was reviewed across 11 categories. Of the categories, six were rated as Excellent, and the remainder were placed as Very Good. Additionally, the reviewer noted, "Excel Contractors was a great firm to work with during the Tu Hogar Renace program. Their experience showed with an adaptable management team. The demands of large-scale housing programs change over time, and Excel's leadership team did a great job adapting to the program's needs. I recommend working with them and look forward to working with them again."
Other Construction Projects
Semiconductor
Linde TSMC Semiconductor
Construction, Civil, Mechanical, Electrical & Instrumentation, Fabrication
View Project
Oil and Gas, Renewable Energy
Valero Diamond Green Diesel 3
Construction, Mechanical, Electrical & Instrumentation
View Project
Renewable Energy
OCI Nitrogen
OCI announces partnership with Louisiana and Texas-based EXCEL Group to construct all elements of a new Beaumont facility.
Construction
View Project
Oil and Gas
Exxon/XTO Cowboy Project
EXCEL completed the construction of a grassroots cryogenic gas plant in New Mexico.
Construction, Civil, Structural, Mechanical, Electrical & Instrumentation, Fabrication
View Project
Oil and Gas
EXXON #12 Deprop Turnaround
Excel Performed Fabrication and Mechanical Work.
Construction, Mechanical, Turnarounds, Fabrication
View Project
Chemical / Petrochemical
BASF PGM Refinery
Self-Performing Civil, Mechanical, Structural, and E&I
Construction, Civil, Structural, Mechanical, Electrical & Instrumentation
View Project
Space & Aviation
Atlas V Project
Lockheed Martin, Complex 3-E Vandenburg Air Force Station and Complex 41 Cape Canaveral Air Force Station renovation projects
Construction, Electrical & Instrumentation
View Project
Technology
LIGO Project
LIGO consists of two ground-based Michelson interferometers with Fabry-Perot arm cavities, operated in unison to detect gravitational waves directly.
Construction
View Project
Oil and Gas
KTI-Saudi Aramco Heater Revamp
EXCEL's scope on the KTI-Saudi Aramco Heater Revamp was demolition, performed pipe fabrication, and installed pipe and structural steel on the platformer consisting of four heaters.
Construction, Fabrication
View Project
Terminals
TDC Bitumen Unloading Project
As an EPC contractor for TDC/Genesis Energy, EXCEL provided a total design and construction solution for their Bitumen Unloading facility.
Construction
View Project
Terminals, Midstream
Kinder Morgan Geismar Logistics Center
As general contractor for the Kinder Morgan Geismar Logistics Center, EXCEL provided a total construction solution for Kinder Morgan's terminal project.
Construction
View Project
Chemical / Petrochemical
Nalco R-1050 Reactor Replacement Expansion
EXCEL worked as the general contractor for this EPC contract to replace the 25-year-old R-1050 reactor with a larger, more efficient one.
Construction
View Project
Food & Beverage
Cruzan CMS Recovery Project Expansion
EXCEL worked as the general contractor for all civil, structural, mechanical, electrical, and instrumentation work for the Cruzan Rum Facility.
Construction, Civil, Structural, Mechanical, Electrical & Instrumentation, Fabrication
View Project
Chemical / Petrochemical
Westlake Control Room Upgrade
EXCEL was selected as the general contractor for the Westlake Control Room Upgrade Project.
Construction
View Project