Electrical & Instrumentation

P66 Bayou & GRP

The P66 Lake Charles "Project Bayou GRE" was a substantial specialty electrical and instrumentation project that involved construction on four units simultaneously, all of which were live and operating, showcasing the team's capability to work in highly sensitive environments.

Location

Lake Charles, LA

Contract Value

$8,000,000

Duration

16 Months

Project Scope

The project included the installation of approximately 3,200 linear feet of cable tray, pulling approximately 253,000 linear feet of cable, and installing around 35,000 feet of conduit. Throughout the project, EXCEL was tasked with additional work added almost daily, leading to change orders that nearly doubled the original scope, schedule, and budget.

Markets

Oil and Gas

Project Status

Complete

Project Description

The P66 Lake Charles Bayou & GRP Project represents the pinnacle of specialty electrical and instrumentation work within the complex and demanding environment of the Lake Charles Refinery (LCR). Beginning in November 2022 and concluding in April 2024, this 16-month project was a comprehensive revamp of the Premium Coker Number 1 Unit. It was designed to enhance the refinery's capability to process various slurry feeds while significantly upgrading its electrical infrastructure. With a focus on precision and safety, EXCEL delivered exceptional results, meeting stringent deadlines and exceeding project expectations despite numerous challenges.

Quantity Installation Summary

Bus Duct 60
Large Transformer 7
Capacitor Banks 4
Cable Tray 10,456 LF
Tubing Tray 2,430 EA
Conduit 81,260 EA
Power and Control Cable 286,156 LF
Tubing 14,370 EA

Other Electrical & Instrumentation Projects

P66 Borger
Complete

Oil and Gas

P66 Borger

The expansion of the P66 Borger Refinery was designed to boost the facility's processing capabilities by incorporating new crude heaters and related infrastructure. EXCEL Group was contracted to carry out the Electrical and Instrumentation (E&I) tasks, which included installing critical systems to support the new equipment.

Electrical & Instrumentation

View Project

Complete

LNG

Cameron LNG

EXCEL provided E&I installation for Cameron LNG's Train 3. The project included 588,531 man-hours to install 34.5kv, 15kv, 5kv, 480v and UPS power distribution, instrument DCS and control systems, instrument and device installation and check-out. 

Electrical & Instrumentation

View Project

Dow Samsung Chlorine Project
Eagle Award
Complete

Chemical / Petrochemical

DOW-SAMSUNG Chlorine #7 Falcon Project

As a specialty electrical and instrumentation contractor for the Dow-Samsung Chlorine #7 Project Falcon, the largest industrial project at the time.

Electrical & Instrumentation

View Project

Complete

Oil and Gas

Marathon Turnaround

Excel Provided Electrical & Instrumentation Services

Electrical & Instrumentation

View Project

Orascom Methanol Plant
Complete

Chemical / Petrochemical

Orascom Methanol Plant

EXCEL completed the E&I construction for the world-class Methanol Plant owned by Natgasoline

Electrical & Instrumentation

View Project

fccu block turnaround
Complete

Oil and Gas

Hovensa Oil Refinery FCCU Block Turnaround

EXCEL was the general contractor for all electrical and instrumentation work for the Hovensa Oil Refinery

Electrical & Instrumentation, Turnarounds

View Project

Get Started

Consult with an expert. Get a customized plan and budgetary estimate.

Want to stay up to date? Sign up to receive project updates and company news in your inbox.

We care about the protection of your data. Read our Privacy Policy.